Workorder
Date: 06-23-2026
Address: 805 West Mcgee St B
Greensboro, NC 27401
Manager: Pink Team
Status: 15 of 16 completed
Link:
Notes
Particle board kitchen subfloor is completely saturated and covered in mold.
Active Tasks - 1
Replace damaged flooring in kitchen and dining room. Replace those 2 areas (10x18) with LVP and transition into living room. The new floor will not match the existing flooring
Completed Tasks - 15
Repair closet doors in bed1. Requires new hardware
Replace broken outlet cover in bed1
Tighten towel bars in guest and primary bath
Replace door stops as needed. Bed1 x2, guest bath x1, and primary bed x3
Scrape and recaulk tub in guest bath and primary bath
Reinstall closet door and replace rollers in primary bedroom
Replace trim on the front of the primary bathroom tub
Demo tile flooring in guest bath 6x6 then haul away. Replace rotten subfloor under toilet. Install new tile substrate/tile. Reset toilet
Adjust exterior door to balcony in primary bedroom. Rubs jamb and deadbolt does not catch
Replace shower head in guest bath
Install string to pull down attic steps
Repair loose stairwell railing
Install 2 bulbs in kitchen light
Repair/replace accordion door next to fridge
Install 2 microwave bulbs